Sixteen days to the DRC: why the North-South Corridor is still failing
Sixteen days to the DRC: why the North-South Corridor is still failing
The North-South Corridor keeps Southern Africa’s trade moving, but border delays still cripple efficiency. MIKE FITZMAURICE examines what must change to transform this vital regional artery over the next decade.
For South African transporters moving freight north into Zambia and the Democratic Republic of Congo (DRC), distance is only part of the problem. A journey from Durban to Kasumbalesa currently takes an average of around 15 days and 21 hours northbound; of that time, about 130 hours can be lost at borders. That is the central challenge facing the North-South Corridor.
Southern Africa has spent billions improving roads, bridges and border infrastructure. Yet trucks continue to lose days waiting for documents, inspections, system availability and permission to move. If this corridor is to fulfil its potential, the next decade cannot simply be about pouring more asphalt. It has to be about removing friction.
A corridor of enormous importance
Launched in 2009 as part of a COMESA-EAC-SADC Aid for Trade programme, the North-South Corridor has become one of the region’s most important trade arteries. The core route between Durban and Kolwezi extends for about 3,000km, while the wider multimodal network, including its various spurs, stretches for more than 10,000km. It links South Africa with Zimbabwe, Botswana, Zambia and the DRC, with connections extending into Mozambique, Malawi and Tanzania.
For South African exporters and transporters, the corridor provides access to some of the continent’s fastest-growing mining, agricultural and consumer markets. It also runs through the Copperbelt, major farming regions and areas served by regional electricity and telecommunications networks.
Yet despite its economic importance, much of the freight moving along it remains heavily dependent on road transport… and road transport is only as efficient as its slowest border.
Two ways north
From South Africa, freight generally moves north through one of two main routes. The first runs through Musina and Beitbridge into Zimbabwe before continuing via Harare and Chirundu into Zambia. The alternative crosses into Botswana at Groblersbrug/Martins Drift, passing through Francistown and Kazungula before reaching Livingstone and Lusaka.
From Zambia, both routes ultimately feed into the Copperbelt and converge towards Kasumbalesa, the critical border crossing into the DRC. From there, freight continues towards Lubumbashi, Kolwezi and the heart of Central Africa’s mining economy.
Durban and Richards Bay remain major gateways for this trade, but competition from other ports is intensifying. Dar es Salaam has captured substantial volumes of DRC copper traffic through the Nakonde-Tunduma route. Walvis Bay has become increasingly competitive for Copperbelt minerals, while Beira and Maputo provide additional alternatives.
That competition should concern South Africa. Cargo owners do not owe Durban their business. If another port and corridor can move freight faster, more predictably and at lower cost, volumes will shift.
The real cost is measured in time
The 2024/25 SADC Time Release Study recorded an average northbound journey of 15 days, 21 hours and five minutes from Durban to Kasumbalesa. Border delays account for around 36% of total transit time and a significant share of operating cost.
For a transporter, time spent standing still is not free. The truck continues to incur finance, driver, insurance and operating costs. Loads are delayed; vehicle utilisation falls; customers wait longer and another revenue-earning trip is pushed further into the future. Industry estimates place the cost of border delays at a minimum of around US$1,250 per truck per trip, with some estimates considerably higher.
The experience also varies dramatically from one border to another. At Beitbridge, median northbound processing times may be measured in hours, yet the worst-performing movements can stretch into several days. At Kasumbalesa, congestion can be far more severe. Monitoring in 2024 recorded exceptionally long northbound delays from Zambia into the DRC, while journeys in the opposite direction were generally much quicker. That imbalance exposes a recurring problem on African trade corridors: infrastructure improvements alone cannot compensate for inconsistent procedures.
Billions spent, but trucks still wait
There has been substantial investment along the corridor. The Harare-Masvingo-Beitbridge road has been rehabilitated; Beitbridge itself underwent a US$241 million modernisation programme. Kazungula Bridge replaced the old ferry crossing between Botswana and Zambia, removing one of the corridor’s most notorious historical bottlenecks. Further north, the African Development Bank has funded improvements to the Chinsali-Nakonde section of Zambia’s Great North Road, while work around Chirundu includes climbing lanes and road realignment aimed at improving safety.
These projects are necessary: better roads reduce vehicle operating costs, improve safety and make journeys more predictable. However, a truck travelling on a first-class road achieves very little if it reaches the border and sits there for two days. Southern Africa therefore needs to stop treating road infrastructure and border efficiency as separate problems.
Beitbridge needs the next leap
Beitbridge remains one of the most important crossings on the entire corridor. Its physical infrastructure has improved considerably, but the next challenge is operational integration. A genuine one-stop border post (OSBP) arrangement would reduce duplication by allowing authorities on both sides to coordinate processes more effectively.
Queue management along the N1 also needs greater attention, while scanning should increasingly move towards intelligence-led and risk-based processes rather than unnecessarily treating every movement as equally suspicious.
Duplicate inspections, weighbridge processes and charges all add time and cost. If every agency adds only a small delay, the combined effect can become enormous.
Chirundu cannot live on its reputation
Chirundu became Africa’s first OSBP and was once held up as a model of what regional trade facilitation could achieve – but infrastructure ages and systems fail. Reliable scanners, customs-system uptime, harmonised operating hours and effective data exchange between Zimbabwe and Zambia are essential if the border is to retain its role as a showcase for integration. An OSBP is not truly one-stop if a transporter still has to duplicate information or wait for separate systems to communicate.
Groblersbrug needs resilience
The alternative route through Groblersbrug and Martins Drift has become increasingly important (particularly when Beitbridge is congested), but it has vulnerabilities of its own. Flooding of the Limpopo can disrupt the crossing, while inadequate parking and staging facilities place additional pressure on operators.
If Southern Africa wants credible alternative routes, those alternatives must remain usable during adverse weather and periods of unusually high traffic. All-weather staging facilities, adequate parking and flood resilience are therefore not secondary infrastructure; they form part of corridor reliability.
Kasumbalesa remains the monster bottleneck
At the northern end of the corridor, Kasumbalesa remains perhaps its toughest challenge. The border is the gateway between Zambia and the DRC and sits at the convergence of several important regional trade corridors. Volumes are enormous and the consequences of delay are felt far beyond the border itself.
The solution requires better data exchange between Zambian and Congolese customs platforms so that information does not have to be captured repeatedly. Round-the-clock operations, dedicated bypass infrastructure and greater regulatory consistency would also reduce congestion. Transporters can plan around distance. What they struggle to plan around is a border where requirements, operating conditions or waiting times change without warning.
Technology can remove friction
The corridor’s next major gains may come less from concrete and more from data. Electronic single windows can allow traders and transporters to submit information once, rather than repeatedly providing the same documentation to different government agencies. Electronic cargo tracking and seals can provide customs administrations with greater confidence that goods have not been diverted. Automatic number-plate recognition can speed vehicle identification, while AI can assist with X-ray image analysis and risk profiling.
GPS data can also be used to predict congestion and allocate border slots before trucks arrive. Even tariff classification can increasingly be supported by digital tools, reducing some of the disputes that delay consignments.
None of these technologies should simply add another layer of bureaucracy. The objective must be fewer processes, not digital versions of the same duplication.
What could the corridor look like by 2036?
A credible target for the next decade would be to reduce Durban-Kasumbalesa transit time from almost 16 days to five or six days. Border delays should fall from around 130 hours to less than 24. That would fundamentally change the economics of regional transport.
The corridor could also become less dependent on trucks for appropriate bulk movements, with a greater share of minerals shifting to rail and alternative export corridors. At the same time, logistics parks around Chirundu and Kasumbalesa could support warehousing, consolidation and value-added services rather than functioning purely as places where trucks wait.
Regional documentation could also be simplified. Imagine one electronic consignment note, one regional customs bond and one recognised electronic seal covering a load from Durban to Lubumbashi. That is the level of integration Southern Africa should be pursuing.
Governments need to stop solving half the problem
Governments across the corridor need to coordinate legislation and border procedures, rather than pursuing reforms independently. One-stop border legislation must work on both sides of a boundary, transit declarations and regional bonds should be harmonised and border agencies should operate according to coordinated 24-hour systems where freight volumes justify it.
Road-maintenance funding also needs to be protected, while public-private infrastructure projects should be structured carefully enough that tolls and access charges do not make regional trade prohibitively expensive.
Development partners have a role too. Funding should not focus overwhelmingly on roads and bridges while ignoring the technology, electricity supply, connectivity and customs-system interoperability required to make borders work.
Success should ultimately be judged by measurable outcomes. How long did the truck take to cross? How many times was the same information requested? How many inspections were genuinely necessary? How predictable was the journey? Those measurements tell us far more about corridor performance than the number of kilometres resurfaced.
The test is simple
The North-South Corridor does not need another grand vision that exists only in policy documents. It needs trucks to move. South Africa, Zimbabwe, Botswana, Zambia and the DRC all benefit when goods travel more efficiently between their markets. Transporters benefit through better utilisation, exporters gain through lower logistics costs and consumers ultimately benefit from more efficient supply chains.
Roads and bridges remain essential, but they are only part of the equation. The real test of the North-South Corridor’s success will be much simpler: can a truck complete a journey from Durban to the DRC without repeatedly stopping to provide the same information to different authorities? If Southern Africa can achieve that, turning a 16-day journey into six days may no longer seem ambitious… it may simply become normal.